Salt Mist Corrosion Testing of Photovoltaic (PV) Modules
Test Condition
Severity 1: 4 cycles with 7 days of each cycle including 2 hours of salt mist spray followed by 7 days of storage under high humidity condition
Severity 3 / 4 / 5 / 6: 1 / 2 / 4 / 8 cycles with 7 days of each cycle Including initial 4 days with 2 hours of salt mist spray and 22 hours of storage under high humidity condition every day, followed by 3 days of storage under a standard atmosphere
Pass Criteria
a) No evidence of major visual defects
b) Pass insulation test
c) Pass wet leakage current test
d) Degradation of maximum power output < 5%